Anandi Construction vs. The General Manager
Court:Allahabad High Court (Allahabad)
Judge:Hon'ble Saumitra Dayal Singh
Case Type:Unrecognized case type
Act & Section:Arbitration And Conciliation Act - 11(6)
Reg no:101/2018
Filing no:90008/2018
CNR:UPHC011662272018
Case Category:Writ Petition Under The Arbitration And Conciliation Act 1996
Judicial Section:Unknown
Bench Type:Single Bench
Parties & Advocates
Petitioner
1
Anandi Construction
Petitioner Advocate
1
Ashutosh Pandey
Respondents
1
The General Manager
2
North Eastern Railway
3
3 Ors
Respondent Advocate
1
Rajnish Kumar Rai
Case History with Orders
Unknown - 7 Nov 2019
Final Status
7 Nov 2019
Unknown - 7 Nov 2019
Final Status
8 Nov 2019
For Order
Before: Hon'Ble Saumitra Dayal Singh
8 Nov 2019
For Order
Before: Hon'Ble Saumitra Dayal Singh
7 Nov 2019
Disposed
Before: Hon'Ble Saumitra Dayal Singh
14 Oct 2019
For Order
Before: Hon'Ble Saumitra Dayal Singh
14 Oct 2019
For Order
Before: Hon'Ble Saumitra Dayal Singh
12 Feb 2019
For Order
Before: Hon'Ble Govind Mathur
12 Feb 2019
For Order
Before: Hon'Ble Govind Mathur
2 Jan 2019
For Order
Before: Hon'Ble Saumitra Dayal Singh
2 Jan 2019
For Order
Before: Hon'Ble Saumitra Dayal Singh
17 Dec 2018
For Order
Before: Hon'Ble Saumitra Dayal Singh
7 Dec 2018
For Order
Before: Hon'Ble Saumitra Dayal Singh
7 Dec 2018
For Order
Before: Hon'Ble Saumitra Dayal Singh
19 Sept 2018
For Admission
Before: Hon'Ble Ashok Kumar
19 Sept 2018
For Admission
Before: Hon'Ble Ashok Kumar
10 Sept 2018
First Hearing
Initial hearing scheduled
10 Sept 2018
Fresh
Before: Hon'Ble No Tied Up
10 Sept 2018
First Hearing
Initial hearing scheduled
Fresh
Before: Hon'Ble No Tied Up
7 Sept 2018
Case Registered
Registration No: 101/2018
7 Sept 2018
Case Registered
Registration No: 101/2018
Case Filed
24 Aug 2018
Filing No: 90008/2018
Purpose: For Order
24 Aug 2018
Case Filed
24 Aug 2018
Filing No: 90008/2018
Purpose: For Order
Interlocutory Applications (IA) (1)
IA/1/2018 Classification : Listing Application
Particular: Listing Application
Filed by: M/S ANANDI CONSTRUCTIONTHE GENERAL MANAGER, NORTH EASTERN RAILWAY AND 3 ORS
Filing Date: 2018-11-27
Remark: 28-11-2018
Share This Case