öITEM NO.13 REGISTRAR COURT.2 SECTION XVII
S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS CIVIL APPEAL NO(s). 10868 OF 2010 BEFORE THE REGISTRAR SUNIL THOMAS
POWERGRID CORP.OF INDIA LTD. Appellant (s)
VERSUS
CEN.ELECT.REGUL.COMMN.& ORS. Respondent(s)
WITH Civil Appeal NO. 4 of 2011 Civil Appeal NO. 5846 of 2011 (With office report)
Date: 25/04/2012 This Appeal was called on for hearing today.
For Appellant(s)
Mr. Pramod Dayal,Adv.
For Respondent(s) Mr.Manish Goswami,adv. M/S Map & Co.,Adv.
Mr.Sapam Biswajit Meitei,adv. Mr.Khwairakpam Nobin Singh ,Adv
UPON hearing counsel the Court made the following O R D E R
In Civil Appeal No.5846/11 all the respondents have been served by dasti. Respondent No.2 has also appeared. No appearance for the remaining respondents. Hence, service is complete. In Civil Appeal No.10868/10 respondent No.3 is awaited and respondent Nos. 1 & 8 are awaited in Civil Appeal No.4/11.
Contd....2 ITEM NO.13 -2-
Ld.counsel for the appellant submits that the respondents are common in all the above cases and in the light of service of notice on all the respondents in Civil Appeal No.5846/11 the service of the unserved respondents in Civil Appeal No.10868/10 and Civil Appeal No.4/11 shall be deemed as complete. On verifying the file it is seen that the above unserved respondents have been served in other connected matters, either by post or dasti or by both. Hence, service is deemed as complete. Respondent No.6 is granted four more weeks time as a last chance for filing counter affidavit. List the matter on 12.07.2012.
(Sunil Thomas) Registrar