Bina Basnett vs. The State Of Sikkim
AI Summary
Get an AI-powered analysis of this court order
Order Issued After Hearing
Purpose:
Case Registered
Listed On:
25 Sept 2023
Original Order Copy
Get a certified copy of this order
Order Text
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. OF 2023 (@ Diary No. 32544/2022)
BINA BASNETT
APPELLANT(S)
VERSUS
STATE OF SIKKIM & ORS.
$$
ORDER
Delay condoned.
This appeal impugns the order dated 10.05.2022 passed by the National Green Tribunal (NGT), Eastern Zone Bench, Kolkata. Paragraph 5 of the impugned order states that the proceedings initiated before the NGT were premature, as the construction, subject matter of the proceedings, had not yet reached 5% storeys. We do not agree with the said finding and reason to dismiss the petition, as the construction post the permissions had admittedly commenced. It is informed at the bar that the construction is now complete.
Without expressing any opinion on the merits of the case, we set aside the impugned order and restore O.A. no. 38/2022/EZ to its original position, to be decided afresh without being influenced by INSTANCE METALOR STRUCK
Learned counsel for the respondents have submitted that there has been a considerable delay in listing of the present appeal on account of lapses on the part of the appellant – Bina Basnett. This is disputed by the appellant - Bina Basnett, who also submits that the plea is contradictory. We express no opinion in this regard. As an order of remand, hearing and decision is being passed, all pleas and contentions of the parties are left open.
The appeal is allowed and disposed of in the above terms. No costs. Parties will appear before the NGT on 18.10.2023, when a date of hearing will be fixed.
Pending application(s), if any, shall stand disposed of.
.................J. (SANJIV KHANNA)
.................J. (S.V.N. BHATTI)
NEW DELHI; SEPTEMBER 25, 2023.
ITEM NO.61 COURT NO.3 SECTION XVII
S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS
CIVIL APPEAL Diary No. 32544/2022
(Arising out of impugned final judgment and order dated 10-05-2022 in OA No. 38/2022 passed by the National Green Tribunal, Eastern Zone Bench, Kolkata)
BINA BASNETT Petitioner(s)
VERSUS
STATE OF SIKKIM & ORS. Respondent(s)
(IA No.171217/2023-CONDONATION OF DELAY IN FILING and IA No.171216/2023-STAY APPLICATION and IA No.171219/2023-CONDONATION OF DELAY IN REFILING / CURING THE DEFECTS)
Date : 25-09-2023 This matter was called on for hearing today.
CORAM :
HON'BLE MR. JUSTICE SANJIV KHANNA HON'BLE MR. JUSTICE S.V.N. BHATTI
For Petitioner(s)
Mr. Sukumar Pattjoshi, Sr. Adv.
- Mr. Prakash Kumar, Adv.
- Mr. Pratap Shanker, Adv.
- Mr. Rahul Ranjan Singh, Adv.
- Mr. Ankit Kumar, Adv.
- Mr. Manoj Bhardwaj, Adv.
- Mr. Swetank Shantanu, AOR
For Respondent(s)
- Mr. Basava Prabhu S. Patil, Sr. Adv./AG Mr. Sameer Abhyankar, Adv./AOR
- Ms. Nishi Sangtani, Adv.
- Ms. Vani Vandana Chhetri, Adv.
- Mr. Naman Jain, Adv.
- Mr. Pinaki Misra, Sr. Adv.
- Mr. Sanjay Upadhyay, Adv.
- Ms. Mayuri Raghuvanshi, AOR
- Ms. Mansi Bachani, Adv.
- Ms. Sonali Sen Gupta, Adv.
- Mr. Kazi Sangay Thupdan, Adv.
- Mr. Soumitra Jaswal, Adv.
- Mr. Vyom Raghuvanshi, Adv.
Mr. Balbir Singh, ASG
Mr. Shyam Gopal, Adv./AOR
UPON hearing the counsel the Court made the following O R D E R
Delay condoned.
The appeal is allowed and disposed of in terms of the signed order.
Pending application(s), if any, shall stand disposed of.
(DEEPAK GUGLANI) (R.S. NARAYANAN) AR-cum-PS ASSISTANT REGISTRAR (signed order is placed on the file)