COURT NO.1
SUPREME COURT OF INDIA RECORD OF PROCEEDINGS
Petition(s) for Special Leave to Appeal (C) No(s).17457/2016
(Arising out of impugned final judgment and order dated 10/02/2016 in CMA No.959/2015 passed by the High Court of Judicature at Hyderabad for the State of Telangana and the State of Andhra Pradesh)
SRI SUMANJALI PROJECTS PVT. LTD. AND ANR. Petitioner(s)
VERSUS
SYED IBRAHIM HASSAN KAZMI @ ASLAM KAZMI AND ORS. Respondent(s)
(With interim relief and office report)
Date: 20/02/2017 This petition was called on for hearing today.
$CORAM$ :
HON'BLE THE CHIEF JUSTICE HON'BLE DR. JUSTICE D.Y. CHANDRACHUD HON'BLE MR. JUSTICE SANJAY KISHAN KAUL
- For Petitioner(s) Mr. Vijay Kumar, Adv. Dr. Sushil Balwada, Adv.
- For Respondent(s) Mr. Amit K. Nain, Adv. Mr.Kapil Hooda, Adv.
- Upon hearing the counsel the Court made the following ORDER
Learned counsel representing the respondents has circulated a letter seeking an adjournment, so as to enable the respondents to file counter affidavit.
Prayer is allowed. Counter affidavit be filed within two weeks, as prayed for.
List for hearing thereafter.
<table><tbody>HATISH KUMAR YADAV)</tbody> $AR-CUM-PS$(RENUKA SADANA) ASSISTANT REGISTRAR