Union Of India Thr. Chief Engineer (Construction) 1 vs. B. M. Construction Company Thr. Proprietor Bal Kishan Sharma
Court:Supreme Court of India
Judges:Hon'ble A.M. Khanwilkar, Hon'ble Ajay Rastogi
Case Type:Civil Appeal
Reg no:3314/2019
Filing no:8895/2018
CNR:SCIN010088952018
Parties & Advocates
Petitioners
1
Union Of India Thr. Chief Engineer (construction) 1
2
General Manager North Western Railway
3
Deputy Chief Engineer (construction) 1 North Western Railway
Petitioner Advocate
1
Anil Katiyar
Respondent
1
B. M. Construction Company Thr. Proprietor Bal Kishan Sharma
Respondent Advocate
1
Geetanjali Mohan
Case History with Orders
Disposed - 29 Mar 2019
Final Status
29 Mar 2019
Disposed - 29 Mar 2019
Final Status
29 Mar 2019
Case Registered
Registration No: 3314/2019
29 Mar 2019
For Judgement
Purpose:Fixed Date By Court
Category:Unknown
Before:Hon'ble A.M. Khanwilkar, Hon'ble Ajay Rastogi
List In:Judge
Disposed off
29 Mar 2019
Case Registered
Registration No: 3314/2019
For Judgement
Purpose:Fixed Date By Court
Category:Unknown
Before:Hon'ble A.M. Khanwilkar, Hon'ble Ajay Rastogi
List In:Judge
Disposed off
12 Feb 2019
After Notice (For Admission) - Civil Cases
Purpose:Fixed Date By Court
Category:Unknown
Before:Hon'ble A.M. Khanwilkar, Hon'ble Ajay Rastogi
List In:Judge
Heard & Reserved
12 Feb 2019
After Notice (For Admission) - Civil Cases
Purpose:Fixed Date By Court
Category:Unknown
Before:Hon'ble A.M. Khanwilkar, Hon'ble Ajay Rastogi
List In:Judge
Heard & Reserved
29 Jan 2019
Disposal/final Disposal At Admission Stage - Civil Cases
Purpose:Next Week / Week Commencing / C.o.week
Category:Unknown
Before:Hon'ble A.M. Khanwilkar, Hon'ble Ajay Rastogi
List In:Judge
29 Jan 2019
Disposal/final Disposal At Admission Stage - Civil Cases
Purpose:Next Week / Week Commencing / C.o.week
Category:Unknown
Before:Hon'ble A.M. Khanwilkar, Hon'ble Ajay Rastogi
List In:Judge
10 Dec 2018
Disposal/final Disposal At Admission Stage - Civil Cases
Purpose:Fixed Date By Court
Category:Unknown
Before:Hon'ble A.M. Khanwilkar, Hon'ble Hemant Gupta
List In:Judge
Week Commencing [21-01-2019], List On NMD [ANY]
10 Dec 2018
Disposal/final Disposal At Admission Stage - Civil Cases
Purpose:Fixed Date By Court
Category:Unknown
Before:Hon'ble A.M. Khanwilkar, Hon'ble Hemant Gupta
List In:Judge
Week Commencing [21-01-2019], List On NMD [ANY]
12 Sept 2018
Disposal/final Disposal At Admission Stage - Civil Cases
Purpose:Fixed Date By Court
Category:Unknown
Before:Hon'ble Hon'Ble The Chief Justice, Hon'ble A.M. Khanwilkar, Hon'ble Hon'Ble The Chief Justice
List In:Judge
List After (Weeks) [1]
12 Sept 2018
Disposal/final Disposal At Admission Stage - Civil Cases
Purpose:Fixed Date By Court
Category:Unknown
Before:Hon'ble Hon'Ble The Chief Justice, Hon'ble A.M. Khanwilkar, Hon'ble Hon'Ble The Chief Justice
List In:Judge
List After (Weeks) [1]
21 Aug 2018
After Notice (For Admission) - Civil Cases
Purpose:Fixed Date By Court
Category:Unknown
Before:Hon'ble Hon'Ble The Chief Justice, Hon'ble A.M. Khanwilkar, Hon'ble Hon'Ble The Chief Justice
List In:Judge
List for Final Hearing/Disposal At Misc. Stage, List On (Date) [12-09-2018]
21 Aug 2018
After Notice (For Admission) - Civil Cases
Purpose:Fixed Date By Court
Category:Unknown
Before:Hon'ble Hon'Ble The Chief Justice, Hon'ble A.M. Khanwilkar, Hon'ble Hon'Ble The Chief Justice
List In:Judge
List for Final Hearing/Disposal At Misc. Stage, List On (Date) [12-09-2018]
20 Jul 2018
Service/compliance-before Registrar(j)
Purpose:Fixed Date By Court
Category:Unknown
Before:Registrar (J) - Ii
List In:Registrar
20 Jul 2018
Service/compliance-before Registrar(j)
Purpose:Fixed Date By Court
Category:Unknown
Before:Registrar (J) - Ii
List In:Registrar
20 Jul 2018
Service/compliance-before Registrar(j)
Purpose:Fixed Date By Court
Category:Unknown
Before:Registrar (J) - Ii
List In:Registrar
Service/compliance-before Registrar(j)
Purpose:Fixed Date By Court
Category:Unknown
Before:Registrar (J) - Ii
List In:Registrar
23 Apr 2018
First Hearing
Initial hearing scheduled
23 Apr 2018
Service/compliance-before Registrar(j)
Purpose:Fixed Date By Court
Category:Unknown
Before:Registrar (J) - Ii
List In:Registrar
23 Apr 2018
First Hearing
Initial hearing scheduled
Service/compliance-before Registrar(j)
Purpose:Fixed Date By Court
Category:Unknown
Before:Registrar (J) - Ii
List In:Registrar
Case Filed
9 Mar 2018
Filing No: 8895/2018
9 Mar 2018
Case Filed
9 Mar 2018
Filing No: 8895/2018
Interlocutory Applications (IA) (1)
44291/2018
Particular: CONDONATION OF DELAY IN FILING
Filed by: ANIL KATIYAR
Filing Date: 2018-03-26
Tagged Matters (17)
4476/2018(06-03-2018 12:00 AM)C.A. No. 003303 / 2019 Registered on 29-03-2019SLP(C) No. 006312 - / 2018 Registered on 06-03-2018 - CA
Petitioner: UNION OF INDIA
Respondent: PARMAR CONSTRUCTION COMPANY
Type: M•Status: P•Entry: 13-12-2018
40491/2017(12-01-2018 12:00 AM)C.A. No. 003304 / 2019 Registered on 29-03-2019SLP(C) No. 002166 - / 2018 Registered on 12-01-2018 - CA
Petitioner: GENERAL MANAGER NORTH WESTERN RAILWAY
Respondent: M/S S.K. CONSTRUCTION
Type: L•Status: P•Entry: 28-03-2019
4970/2018(06-03-2018 12:00 AM)C.A. No. 003307 / 2019 Registered on 29-03-2019SLP(C) No. 006316 - / 2018 Registered on 06-03-2018 - CA
Petitioner: UNION OF INDIA
Respondent: MAYA CONSTRUCTION PVT. LTD.
Type: C•Status: P•Entry: 28-03-2019
4479/2018(06-03-2018 12:00 AM)C.A. No. 003306 / 2019 Registered on 29-03-2019SLP(C) No. 006034 - / 2018 Registered on 06-03-2018 - CA
Petitioner: UNION OF INDIA
Respondent: M/S RAJENDRA PRASAD BANSAL
Type: C•Status: P•Entry: 28-03-2019
3983/2018(16-03-2018 12:00 AM)C.A. No. 003305 / 2019 Registered on 29-03-2019SLP(C) No. 007937 - / 2018 Registered on 16-03-2018 - CA
Petitioner: NORTH WESTERN RAILWAY
Respondent: M/S ANIL TRADING COMPANY
Type: C•Status: P•Entry: 28-03-2019
6612/2018(20-03-2018 12:00 AM)C.A. No. 003312 / 2019 Registered on 29-03-2019SLP(C) No. 007720 - / 2018 Registered on 20-03-2018 - CA
Petitioner: NORTH WESTERN RAILWAY GENERAL MANAGER
Respondent: M/S BHARAT SPUN PIPES AND CONSTRUCTION COMPANY.
Type: C•Status: P•Entry: 28-03-2019
6603/2018(24-03-2018 12:00 AM)C.A. No. 003310 / 2019 Registered on 29-03-2019SLP(C) No. 008019 - / 2018 Registered on 24-03-2018 - CA
Petitioner: NORTH WESTERN RAILWAY
Respondent: M/S BHARAT SPUN PIPES AND CONSTRUCTION COMPANY
Type: C•Status: P•Entry: 28-03-2019
6608/2018(24-03-2018 12:00 AM)C.A. No. 003311 / 2019 Registered on 29-03-2019SLP(C) No. 008021 - / 2018 Registered on 24-03-2018 - CA
Petitioner: NORTH WESTERN RAILWAY GENERAL MANAGER
Respondent: M/S SB SHC MCDPL (JV)
Type: C•Status: P•Entry: 28-03-2019
6611/2018(28-03-2018 12:00 AM)C.A. No. 003309 / 2019 Registered on 29-03-2019SLP(C) No. 008596 - / 2018 Registered on 28-03-2018 - CA
Petitioner: UNION OF INDIA
Respondent: SRI HARSHA CONSTRUCTIONS
Type: L•Status: P•Entry: 28-03-2019
8890/2018(28-03-2018 12:00 AM)C.A. No. 003313 / 2019 Registered on 29-03-2019SLP(C) No. 008598 - / 2018 Registered on 28-03-2018 - CA
Petitioner: UNION OF INDIA
Respondent: M/S RAJENDRA PRASAD BANSAL THR. PARTNER RAJENDRA PRASAD BANSAL
Type: L•Status: P•Entry: 28-03-2019
5712/2018(28-03-2018 12:00 AM)C.A. No. 003308 / 2019 Registered on 29-03-2019SLP(C) No. 008597 - / 2018 Registered on 28-03-2018 - CA
Petitioner: NORTH WESTERN RAILWAY
Respondent: M/S BHARAT SPUN PIPES AND CONSTRUCTION COMPANY
Type: L•Status: P•Entry: 28-03-2019
8905/2018(10-04-2018 12:00 AM)C.A. No. 003315 / 2019 Registered on 29-03-2019SLP(C) No. 009559 - / 2018 Registered on 10-04-2018 - CA
Petitioner: UNION OF INDIA
Respondent: M/S BALAJI BUILDERS AND DEVELOPERS
Type: C•Status: P•Entry: 28-03-2019
8895/2018(10-04-2018 12:00 AM)C.A. No. 003314 / 2019 Registered on 29-03-2019SLP(C) No. 009514 - / 2018 Registered on 10-04-2018 - CA
Petitioner: UNION OF INDIA
Respondent: M/S B.M. CONSTRUCTION COMPANY
Type: C•Status: P•Entry: 28-03-2019
10977/2018(23-04-2018 12:00 AM)C.A. No. 003317 / 2019 Registered on 29-03-2019SLP(C) No. 011417 - / 2018 Registered on 23-04-2018 - CA
Petitioner: UNION OF INDIA
Respondent: M/S KEWAL CONSTRUCTION CO. (JV)
Type: C•Status: P•Entry: 28-03-2019
10980/2018(01-05-2018 12:00 AM)C.A. No. 003318 / 2019 Registered on 29-03-2019SLP(C) No. 011862 - / 2018 Registered on 01-05-2018 - CA
Petitioner: UNION OF INDIA
Respondent: M/S HARINARAYAN KHANDELWAL TH. DIRECTOR
Type: C•Status: P•Entry: 28-03-2019
10973/2018(16-08-2018 04:47 PM)C.A. No. 003316 / 2019 Registered on 29-03-2019SLP(C) No. 022263 - / 2018 Registered on 16-08-2018 - CA
Petitioner: UNION OF INDIA
Respondent: M/S B.M. CONSTRUCTION COMPANY
Type: C•Status: P•Entry: 28-03-2019
8885/2018(29-03-2019 03:50 PM)C.A. No. 003319 / 2019 Registered on 29-03-2019SLP(C) No. 008256 - / 2019 Registered on 29-03-2019 - CA
Petitioner: NORTH WESTERN RAILWAY
Respondent: M/S BHARAT SPUN PIPES AND CONSTRUCTION COMPANY
Type: C•Status: P•Entry: 28-03-2019
Earlier Court Details (3)
Court:
High Court
State:
RAJASTHAN
Case No:
SBAA-96-2014
Order Date:
2017-07-14
Judgment Challenged:
Yes
Judgment Type:
-
Court:
High Court
State:
RAJASTHAN
Case No:
SBCAA-22-2009
Order Date:
2011-12-08
Judgment Challenged:
No
Judgment Type:
-
Court:
High Court
State:
RAJASTHAN
Case No:
SBAA-02-2010
Order Date:
2016-09-09
Judgment Challenged:
No
Judgment Type:
-
Notices (4)
S.No. 1
53326/2018-04-10
Notice Type: letter for certified copy
Name:Through High Court Of Judicature For Rajasthan At Jaipur Rajasthan
Location:
Issue Date:4 Oct 2018
Return Date:7 Feb 2018
Dispatch Date:Pending
S.No. 2
53326/2018-04-10
Notice Type: letter for certified copy
Name:Anil Katiyar-50copy
Location:NEW DELHI, DELHI
Issue Date:4 Oct 2018
Return Date:7 Feb 2018
Dispatch Date:Pending
S.No. 3
53325/2018-04-10
Notice Type: due course notice in SLP
Name:M/S B.M. Construction Company Thr. Proprietor Bal Kishan Sharma
Location:UTTAR PRADESH, GHAZIABAD, Station: Ghaziabad
Issue Date:4 Oct 2018
Return Date:7 Feb 2018
Dispatch Date:18 Apr 2018
S.No. 4
53325/2018-04-10
Notice Type: due course notice in SLP
Name:Anil Katiyar-50copy
Location:NEW DELHI, DELHI
Issue Date:4 Oct 2018
Return Date:7 Feb 2018
Dispatch Date:Pending
Share This Case
Similar Case Search
Same Parties
Union Of India Thr. Chief Engineer (Construction) 1 vs B. M. Construction Company Thr. Proprietor Bal Kishan SharmaUnion Of India Thr. Chief Engineer (Construction) 1General Manager North Western RailwayDeputy Chief Engineer (Construction) 1 North Western RailwayB. M. Construction Company Thr. Proprietor Bal Kishan Sharma
Case Content Last Updated22 Aug 2025, 11:18 am IST