ITEM NO.78 REGISTRAR COURT. 2 SECTION XII-A
S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS
BEFORE THE REGISTRAR SURINDER S. RATHI
Civil Appeal No(s). 3788-3790/2019
EASTERN POWER DISTRIBUTION COMPANY OF ANDHRA PRADESH LTD. & ANR.Appellant(s)
VERSUS
GMR VEMAGIRI POWER GENERATION LTD & ORS. Respondent(s)
(FOR ADMISSION and I.R. )
Date : 09-07-2019 These appeals were called on for hearing today.
For Appellant(s)
Mr. Tarun Gupta, AOR Mr. Abhishek Sharma, Adv.
For Respondent(s)
Mr. E. C. Agrawala, AOR Ms. Neha Agarwal, Adv.
Mr. Mohit D. Ram, AOR Mr. Samarth Kashyap, Adv.
UPON hearing the counsel the Court made the following O R D E R
Service is not complete. Appearing Respondents may file Counter Affidavit within a period of two weeks. However, list before the Hon'ble Court on 30.07.2019 as per Order dated 08th April, 2019.
SURINDER S. RATHI Registrar