SLP CC 5337/15
1
ITEM NO.52 COURT NO.5 SECTION IVA
S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS
Petition(s) for Special Leave to Appeal (C)......CC 5337/2015
(Arising out of impugned final judgment and order dated 03/01/2014 in MFA No. 1243/2010 passed by the High Court of Karnataka at Bangalore)
BANGALORE WATER SUPPLY AND SEWERAGE Petitioner(s) BOARD AND ANR
VERSUS
C.N. KRISHNAMURTHY SINCE DECEASED BY Respondent(s) HIS LRS AND ANR
(With c/delay in filing SLP and office report)
Date: 05/05/2015 This application was called on for hearing today.
CORAM :
Digitally signed by Chetan Kumar Date: 2015.05.05 16:50:45 IST Reason:
HON'BLE MR. JUSTICE DIPAK MISRA HON'BLE MR. JUSTICE PRAFULLA C. PANT
For Petitioner(s)
Mr. S. N. Bhat, AOR
For Respondent(s)
UPON hearing the counsel the Court made the following O R D E R
Mr. S.N. Bhat, learned counsel for the petitioners has submitted that Clause 29 of the Agreement is not an arbitration clause and the same has been so held by a three-Judge Bench in M/s. P. Dasaratharama Reddy Complex vs. Government of Karnataka and Another (2014) 2 SCC 201. Signature Not Verified
Issue notice on the application for condonation of delay, as also on the special leave petition, returnable within ten weeks.
There shall be stay of operation of the judgment passed by the High Court of Karnataka at Bangalore in M.F.A. No.1243 of 2010 (AA), until further orders.
(Chetan Kumar) Court Master
(H.S. Parasher) Court Master