Sri Paran Jyoti Saikia vs. The Assam Power Distribution Company Ltd. And 4 Ors
AI Summary
Get an AI-powered analysis of this court order
Order Issued After Hearing
Purpose:
Admission
Before:
Hon'ble Honourable Mr. Justice Arup Kumar Goswami
Listed On:
18 Apr 2018
Original Order Copy
Get a certified copy of this order
Order Text
GAHC010260952017
THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : WP(C) 2499/2017
SRI PARAN JYOTI SAIKIA S/O- SRI DHARMA SAIKIA, R/O- HOUSE NO. 7, LUTUMA, P.O-BINOVANAGAR, P.S- FATASIL AMBARI, GUWAHATI-781018, DIST-KAMRUPM, ASSAM
VERSUS
1:THE ASSAM POWER DISTRIBUTION COMPANY LTD. and 4 ORS REPRESENTED BY THE MANAGING DIRECTOR, ASSAM POWER DISTRIBUTION COMPANY LTD., BIJULEE BHAWANANNEX BUILDING, PALTAN BAZAR, DIST- KAMRUP, PIN- 781001
2:THE MANAGING DIRECTOR APDCL BIJULEE BHAWANANNEX BUILDING PALTAN BAZAR DIST- KAMRUP PIN- 781001
3:THE CHIEF GENERAL MANAGER APDCL BIJULEE BHAWANANNEX BUILDING PALTAN BAZAR DIST- KAMRUP PIN- 781001
4:THE ALLAHABAD BANK REPRESENTED BY ITS DEPUTY GENERAL MANAGER ZONAL OFFICE G S ROAD OPP BORA SERVICE STATION ULUBARI GUWAHATI PIN- 781007
5:THE DEPUTY GENERAL MANAGER ZONAL OFFICE ALLAHABAD BANK GS ROAD OPP BORA SERVICE STATION ULUBARI GUWAHATI PIN- 78100
Advocate for the Petitioner : MR.K KALITA
Advocate for the Respondent : MR.N J DUTTA
BEFORE HON BLE MR. JUSTICE PRASANTA KUMAR DEKA
ORDER
Date : 18-04-2018
Heard Mr A Sarma, learned counsel, appearing for petitioner. Also heard Mr KD Sarma, learned counsel for respondent 1, 2 and 3.
By order dated 4.4.2018 learned counsel for petitioner Mr A Sarma was asked to produce the extended bank guarantee before this court and today he submits that in the bank guarantee undertaken by the bank it is clear and apparent that the guarantee would remain in force till 4.5.2017 and unless a demand or claim under the said guarantee is made with the bank in writing by 4th May 2017, the right under the said guarantee would be forfeited and the bank would be relieved of and discharged from the liabilities, and said that respondent APDCL had submitted its demand/claim on 25.4.2017, much ahead of the date(4.5.2017), and as such the guarantee undertaken by the bank does not need further extension.
On the other hand, Mr KD Sarma submits that the bank is totally
noncommittal when inquired by the respondent APDCL about extension of the bank guarantee dated 4.8.2016 of Allahabad Bank, the respondent 4.
Respondent bank, which was being represented by the learned counsel Mr S Chamaria, however, is not present when the matter was taken up today.
Considering this, and in order to have a clear understanding of the terms of the bank guarantee, presence of Mr Chamaria is required. List the matter again on 25.4.2018 when he will clarify on the issue raised before this court today.
JUDGE
Na/