D Ramanaiah vs. The State Of Andhra Pradesh

Court:High Court of Andhra Pradesh
Judge:Hon'ble D Ramesh
Case Status:Unknown Status
Order Date:22 Oct 2021
CNR:APHC010383452021

AI Summary

Get an AI-powered analysis of this court order

Order Issued After Hearing

Purpose:

Admission (Municipal Admn.)

Before:

Hon'ble Battu Devanand

Listed On:

8 Oct 2021

Original Order Copy

Get a certified copy of this order

Download True Copy

Order Text

HIGH COURT OF ANDHRA PRADESH :: AMARAVATI

MAIN CASE No: W.P.No.23576 of 2021

PROCEEDING SHEET

SI.<br>No.DATE<b>ORDER</b>OFFICE<br>NOTE.
2.22.10.2021DR, J
In<br>the<br>present writ<br>petition,<br>in
implementation of various Central and State
the<br>schemes,<br>respondents/concerned
Municipalities have issued notifications inviting
tenders for various works. Accordingly, the writ
petitioner has participated in the said tenders,
into agreements with<br>entered<br>concerned
Municipalities, on different dates and they have
completed the works as per the terms of their
agreement. Subsequently, concerned Municipal
Authorities<br>have inspected the works and
prepared the final bills, the same were uploaded
in the CFMS portal. After some time, said bills
were cancelled without assigning any reasons.
The concerned Municipal authorities have tried
to upload once again the final bills, however,
portal was blocked. Despite<br>said<br>repeated
representations made by the writ petitioner,
concerned Municipal authorities expressed their
inability to process the bills. Hence, the present
writ petition.
Learned Government Pleaders for Finance
for Municipal Administration produced<br>and
memo, dated 16.07.2021, directing all the
Commissioners to take necessary action, for
payment of pending bills for completed works
from the available general funds and also placed
G.O.Rt.No.4096,<br>dated<br>03.09.2021,<br>the
releasing<br>Rupees<br>100<br>crores<br>of<br>additional
funds/special<br>funds<br>in<br>relaxation<br>of<br>treasury
control, for payment of pending bills for the
works completed, taken up under SCSP during
the years 2018-19 and 2019-20.
The<br>learned<br>Government<br>Pleaders
requested time to process the bills, in view of
the G.O.Rt.No.40963, dated 03.09.2021, and it
is also submitted by the learned Government
Pleaders that the authorities would consider and
pay the bills, after uploading the same in CFMS
portal. However, this Court did not consider the
request<br>made<br>by<br>the<br>learned<br>Government
Pleaders.
Therefore,<br>respondents 1 to 4, without
taking up the technical objections,<br>are directed
to pay the bills, which are pending since a long
time<br>to<br>the<br>writ<br>petitioner<br>and<br>to<br>submit
compliance report within four weeks.
Post after four weeks.
Office is directed to print the name of
Government Pleader for Municipal Administration
& Urban Development for R1, Standing counsel
for R2 and R3, Government Pleader for Finance
and Planning for R4, in the cause list.
_______<br>DR, J
RD

Share This Order

Case History of Orders

Order(2) - 22 Oct 2021

Interim Order

Viewing

Order(3) - 22 Oct 2021

Interim Order

Click to view

Order(1) - 8 Oct 2021

Interim Order

Click to view