IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (SPECIAL ORIGINAL JURISDICTION)
THURSDAY, THE SEVENTH DAY OF OCTOBER TWO THOUSAND AND TWENTY ONE :PRESENT:
THE HONOURABLE SRI JUSTICE M.VENKATA RAMANA
WRIT PETITION NO: 19851 OF 2021
Between:
V .Ramaiah, S/o. V. Ramanaiah, aged 45 years, Occ. Contractor, R/o .H.No.4/13-B, V.Agraharam, Rachayapeta Gopavaram Mandal, YSR Kadapa District.
...Petitioner
OF
AND
-
- The State of Andhra Pradesh, Rep. by its Principal Secretary, Finance Department, A.P. Secretariat, Velagapudi, Amaravati, Guntur District.
-
- The State of Andhra Pradesh, Rep. by its Principal Secretary, Water Resources (Irrigation)Department, A.P. Secretariat, Velagapudi, Amaravati, Guntur District.
-
- Executive Engineer, Water Resources Department, Kadapa Division, Kadapa, YSR Kadapa District.
-
- Deputy Executive Engineer, Water Resources Department, Irrigation Sub-Division, Proddatur @ Badvel, YSR Kadapa District.
...Respondents
Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue an appropriate writ, order or direction preferably a Writ in the nature of Mandamus declaring the action of the Respondent No.3 in not paying Rs.23,81,163/- to the petitioner for the work done by him under Agreement No.11/2018-19, dated:12.12.2018 i.e., Reconstruction of Check dam across yerra vanka near Yerraballi SC Colony in Atloor Mandal of YSR kadapa District even after a lapse of more than 21/2 years as illegal, arbitrary, unfair, unjust and violative of Article 14 of the Constitution of India and consequently direct the 3rd Respondent to pay Rs. 23,81,163/- to the petitioner.
IA NO: 1 OF 2021
Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the writ petition, the High Court may be pleased to direct the 3rd Respondent to pay Rs. 23,81,163/- to the petitioner in respect of the work " Reconstruction of Check dam across yerra vanka near Yerraballi SC Colony in Atloor Mandal of YSR Kadapa District, "under Agreement No.11/2018-19, dated12.12.2018 executed by the petitioner 2½ years ago, pending disposal of WP 19851 of 2021, on the file of the High Court.
The petition coming on for hearing, upon perusing the Petition and the affidavit filed in support thereof and upon hearing the arguments of Sri M Siva Kumar, Advocate for the Petitioner, GP for Finance & Planning for the Respondent No.1 and GP for Irrigation for Respondent Nos.2 to 4, the Court made the following; ORDER:
"At request of the learned Government Pleader for Irrigation and Command Area Development, for counter, list on 03.11.2021.
If counter is not filed on that day, this Court will be forced to pass an interim order in all the pending interlocutory applications directing the respondents to meet the prayer sought therein. No further time will be granted for filing counter thereafter.
The learned Government Pleader is requested to get a statement prepared relating to this entire batch of cases, where there are instances, which the respondents could process without any difficulty and without any complaint and
where there is requirement of vigilance enquiry on account of the nature of works carried out.
The 3<sup>rd</sup> respondent-Executive Engineer shall get this statement prepared on or before the above date and get it filed through the office of the learned Government Pleader for consideration of this Court."
//TRUE COPY//
SECTION OFFICER FUT AUDIO FAIRT REGISTRAR
ASSISTANT REGISTRAR
Sd/-K.TataRao
To,
-
- The Principal Secretary, Finance Department, State of Andhra Pradesh, A.P. Secretariat, Velagapudi, Amaravati, Guntur District.
-
- The Principal Secretary, Water Resources (Irrigation)Department, State of Andhra Pradesh, A.P. Secretariat, Velagapudi, Amaravati, Guntur District.
-
- Executive Engineer, Water Resources Department, Kadapa Division, Kadapa, YSR Kadapa District.
-
- Deputy Executive Engineer, Water Resources Department, Irrigation Sub-Division, Proddatur @ Badvel, YSR Kadapa District. (1 to 4 by RPAD)
-
- One CC to Sri. M Siva Kumar, Advocate [OPUC]
-
- Two CCs to GP for Finance & Planning, High Court of Andhra Pradesh. [OUT]
-
- Two CCs to GP for Irrigation, High Court of Andhra Pradesh. [OUT]
-
- One spare copy.
MSB
HIGH COURT
$\mathbb{C}^{\mathbb{C}}\subset\mathbb{C}^{\mathbb{C}}\to\mathbb{C}$
$\text{MVR}, \text{J}$
DATED:07/10/2021
ORDER
LIST ON 03.11.2021
WP.No.19851 of 2021
INTERIM DIRECTION