Order Issued After Hearing

Purpose:

Admission (Irrigation)

Before:

Hon'ble Venkateswarlu Nimmagadda

Listed On:

19 Apr 2022

Original Order Copy

Get a certified copy of this order

Download True Copy

Order Text

IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI

TUESDAY, THE NINETEENTH DAY OF APRIL.

TWO THOUSAND AND TWENTY TWO

:PRESENT:

THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA

IA No. 1 OF 2022 IN

WP NO: 10552 OF 2022

Between:

C.Uma Maheshwar Reddy, S/o Siva Reddy, Aged about 55 years, R/o Chintakuntla Village, Gospadu Mandal, Kurnool Dist.

...Petitioner

AND

    1. The State of Andhra Pradesh, Rep. by its Principal Secretary, Irrigation and CAD Department, Secretariat, Amaravathi, Guntur District.
    1. The State of Andhra Pradesh, Rep. by its Principal Secretary, Finance and Planning Department, Secretariat, Amaravathi, Guntur District.
    1. The District Collector, Kurnool.
    1. The Chief Planning Officer, Kurnool.
    1. The Superintending Engineer, RWS and Sanitation Circle, Kurnool.
    1. The Executive Engineer, RWS and S(P) division, Nandyal, Kurnool.

...Respondents

Counsel for the Petitioner:

Counsel for the Respondent Nos 1 & 3 to 6 : Counsel for the Respondent No 2:

SRI M KARIBASAIAH GP FOR IRRI AND CAD (AP) GP FOR FINANCE AND PLANNING

Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased may pleased to direct the respondents to pay the bill amount i.e. Rs.12,33,967/-, payable to the petitioner in respect of work done i.e., construction of 60KL OHSR at Mayalur village, uyyalavada Mandal, vide agreement dated 28-02-2017 pending disposal of the Writ Petition No. 10552 of 2022, on the file of the High Court.

The court while directing issue of notice to the Respondents herein to show cause as to why this application should not be complied with, made the following order. (The receipt of this order will be deemed to be the receipt of notice in the case).

ORDER

"Heard both sides.

In the circumstances, the respondents are directed to pay the approved and final bill amounts due to the petitioner within a period of six (6) weeks from the date of receipt of a copy of this order."

Sd/- K. SRINIVASA RAJU ASSISTANT REGISTRAR

SECTION OFFICER

//TRUE COPY//

To,

    1. The Principal Secretary, Irrigation and CAD Department, Secretariat, State of Andhra Pradesh Amaravathi, Guntur District.
    1. The Principal Secretary, Finance and Planning Department, Secretariat, State of Andhra Pradesh, Amaravathi, Guntur District.
    1. The District Collector, Kurnool.4. The Chief Planning Officer, Kurnool.
    1. The Superintending Engineer, RWS and Sanitation Circle, Kurnool.
    1. The Executive Engineer, RWS and S(P) division, Nandyal, Kurnool. (Addresses 1 to 6 By RPAD)
  • One CC to SRI. M KARIBASAIAH Advocate [OPUC] Two CCs to GP FOR IRRI AND CAD (AP), High Court Of Andhra Pradesh. $[OUT]$

    1. Two CCs to GP FOR FINANCE AND PLANNING, High Court of Andhra Pradesh. [Out]
    1. One spare copy

BSK

HIGH COURT

$\text{NVJ}$

DATED: 19/04/2022

ORDER

IA No. 1 OF 2022 $\overline{\text{IN}}$ WP NO: 10552 OF 2022

DIRECTION

Share This Order

Case History of Orders

Order(3) - 14 Feb 2024

Final Order

Click to view

Order(4) - 14 Feb 2024

Final Order

Click to view

Order(1) - 19 Apr 2022

Interim Order

Click to view

Order(2) - 19 Apr 2022

Interim Order

Viewing