C.Uma Maheshwar Reddy vs. The State Of Andhra Pradesh
AI Summary
Get an AI-powered analysis of this court order
Order Issued After Hearing
Purpose:
Admission (Irrigation)
Before:
Hon'ble Venkateswarlu Nimmagadda
Listed On:
19 Apr 2022
Original Order Copy
Get a certified copy of this order
Order Text
IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
TUESDAY, THE NINETEENTH DAY OF APRIL.
TWO THOUSAND AND TWENTY TWO
:PRESENT:
THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
IA No. 1 OF 2022 IN
WP NO: 10552 OF 2022
Between:
C.Uma Maheshwar Reddy, S/o Siva Reddy, Aged about 55 years, R/o Chintakuntla Village, Gospadu Mandal, Kurnool Dist.
...Petitioner
AND
-
- The State of Andhra Pradesh, Rep. by its Principal Secretary, Irrigation and CAD Department, Secretariat, Amaravathi, Guntur District.
-
- The State of Andhra Pradesh, Rep. by its Principal Secretary, Finance and Planning Department, Secretariat, Amaravathi, Guntur District.
-
- The District Collector, Kurnool.
-
- The Chief Planning Officer, Kurnool.
-
- The Superintending Engineer, RWS and Sanitation Circle, Kurnool.
-
- The Executive Engineer, RWS and S(P) division, Nandyal, Kurnool.
...Respondents
Counsel for the Petitioner:
Counsel for the Respondent Nos 1 & 3 to 6 : Counsel for the Respondent No 2:
SRI M KARIBASAIAH GP FOR IRRI AND CAD (AP) GP FOR FINANCE AND PLANNING
Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased may pleased to direct the respondents to pay the bill amount i.e. Rs.12,33,967/-, payable to the petitioner in respect of work done i.e., construction of 60KL OHSR at Mayalur village, uyyalavada Mandal, vide agreement dated 28-02-2017 pending disposal of the Writ Petition No. 10552 of 2022, on the file of the High Court.
The court while directing issue of notice to the Respondents herein to show cause as to why this application should not be complied with, made the following order. (The receipt of this order will be deemed to be the receipt of notice in the case).
ORDER
"Heard both sides.
In the circumstances, the respondents are directed to pay the approved and final bill amounts due to the petitioner within a period of six (6) weeks from the date of receipt of a copy of this order."
Sd/- K. SRINIVASA RAJU ASSISTANT REGISTRAR
SECTION OFFICER
//TRUE COPY//
To,
-
- The Principal Secretary, Irrigation and CAD Department, Secretariat, State of Andhra Pradesh Amaravathi, Guntur District.
-
- The Principal Secretary, Finance and Planning Department, Secretariat, State of Andhra Pradesh, Amaravathi, Guntur District.
-
- The District Collector, Kurnool.4. The Chief Planning Officer, Kurnool.
-
- The Superintending Engineer, RWS and Sanitation Circle, Kurnool.
-
- The Executive Engineer, RWS and S(P) division, Nandyal, Kurnool. (Addresses 1 to 6 By RPAD)
-
One CC to SRI. M KARIBASAIAH Advocate [OPUC] Two CCs to GP FOR IRRI AND CAD (AP), High Court Of Andhra Pradesh. $[OUT]$
-
- Two CCs to GP FOR FINANCE AND PLANNING, High Court of Andhra Pradesh. [Out]
-
- One spare copy
BSK
HIGH COURT
$\text{NVJ}$
DATED: 19/04/2022
ORDER
IA No. 1 OF 2022 $\overline{\text{IN}}$ WP NO: 10552 OF 2022
DIRECTION